Thalle – Bauer LLC, a joint venture from North Carolina, has been awarded a $320 million contract for the Rough River Dam Safety Modification Phase II project to enhance dam stability and safety.
Contract Award Details
| Contractor: |
Thalle Construction Co. and Bauer Foundation Corp. (Thalle – Bauer LLC) |
| Contract Value: | $320,385,195 |
| Project: | Rough River Dam Safety Modification Phase II |
| Location: | Falls of Rough, Kentucky |
| Contract Number: | W912QR-26-C-A005 |
| Awarding District: | U.S. Army Corps of Engineers, Louisville District |
Work will be performed in Falls of Rough, Kentucky, with an estimated completion date of Dec. 25, 2029.