  • $150M Interagency Mission: USACE Mobile District is delivering over $150 million in mission-critical renovation and repair projects across two premier Gulf Coast installations for NASA and the U.S. Government Publishing Office (GPO).
  • 43-Acre Continuous Roof Replacement: Revitalizing the roof of “America’s Rocket Factory” at the Michoud Assembly Facility in New Orleans, ensuring the facility remains 100% operational during 24/7 manufacturing of Space Launch System (SLS) and Artemis lunar hardware.
  • Secure Production Facility Upgrades: Modernizing GPO’s Stennis Space Center production plant in Mississippi with advanced structural, electrical, and mechanical infrastructure to support next-generation U.S. passport printing.
  • Interagency & International Services: Leveraged through the USACE IIS program to provide military engineering expertise to civilian federal partners without interrupting sensitive daily operations.
  • Key Leadership: Led by Mobile District Commander Col. Kelcey Shaw, Project Engineer Kalif Bell, and IIS Chief Adriel McConnell.

Editor’s Note: The following is from USACE Mobile District, curated by America’s Engineers for general public, commercial contractor, and industry visibility. The original article can be found at the U.S. Army Corps of Engineers news repository.

Leaders from the U.S. Army Corps of Engineers (USACE), Mobile District, recently traveled to the Gulf Coast to engage with local installation leadership and project delivery teams executing more than $150 million in critical renovation and repair projects for the National Aeronautics and Space Administration. The site visits spanned two premier federal hubs: NASA’s Michoud Assembly Facility in New Orleans, Louisiana, and the John C. Stennis Space Center in Hancock County, Mississippi.

During the engagement, Mobile District leaders reviewed construction progress and evaluated safety protocols. They recognized the dedicated USACE engineers, construction representatives, and contractors working behind the scenes to modernize vital national infrastructure.

USACE Mobile District personnel inspect the commercial roof surface and mechanical equipment of the GPO facility at NASA Stennis Space Center.
Members of the U.S. Army Corps of Engineers Mobile District inspect the roof of the U.S. Government Publishing Office facility at the NASA Stennis Space Center in Kiln, Mississippi, Oct. 21, 2026. The Mobile District is executing major structural, mechanical, and electrical upgrades to prepare the secure production facility for next-generation passport printing equipment. The project supports national security credential manufacturing while maintaining continuous operations. (Courtesy photo)

“The IIS program allows USACE Mobile District to utilize our agency’s robust engineering and construction capabilities for the Department of War and expand that benefit to our nation’s federal partners,” said Adriel McConnell, Chief of the Mobile District International and Interagency Services.

Revitalizing “America’s Rocket Factory” at Michoud

At the Michoud Assembly Facility—widely known as “America’s Rocket Factory”—the Mobile District is spearheading a massive infrastructure overhaul. The centerpiece of this effort is revitalizing one of the largest contiguous roofs in the United States, spanning over 43 acres atop the main manufacturing building. Executing a roofing project of this scale along the hurricane-prone Gulf Coast presents a unique engineering challenge: the building must remain 100% operational throughout construction. Beneath the active roof work, NASA and its industry partners continue the sensitive, round-the-clock manufacturing and assembly of large-scale space structures and systems, including components for the Space Launch System (SLS) and Artemis lunar exploration missions.

Through meticulous phasing, strict quality control, and close coordination with NASA facility managers, the USACE project team ensures that critical aerospace production remains completely uninterrupted and protected from the elements.

Expanding Secure Production at Stennis Space Center

Following the Michoud tour, leadership traveled across the state line to NASA’s Stennis Space Center in Mississippi. There, the Mobile District is managing the complex revitalization of another expansive facility supporting the U.S. Government Publishing Office (GPO)—formerly known as the Government Printing Office. The project directly supports the GPO’s urgent requirement to expand and modernize its Secure Production Facility. As one of only two such federal facilities in the nation, the Stennis operation plays an indispensable role in national security and citizen services.

We’re so glad you are here! Like what you’re reading? Make America’s Engineers a Google preferred news source.

USACE teams are executing major structural, mechanical, and electrical upgrades to prepare the facility for next-generation passport printing technology scheduled to come online later next year. Once complete, the modernized plant will significantly bolster the nation’s secure credential manufacturing capacity and resilience.

Interagency Partnership in Action

The dual-site visit underscored the Mobile District’s versatile capabilities as a premier federal engineering partner. Whether safeguarding the assembly of deep-space rockets or modernizing secure printing lines for American travelers, the district’s workforce continues to deliver complex infrastructure solutions on time and within budget.

“Our NASA projects showcase that capability to renovate and restore large building infrastructure ahead of schedule under difficult conditions, where existing operations cannot be impacted,” McConnell said.

This article was originally published by the U.S. Army Corps of Engineers under the title, “Engineering the Future of Space and Security.” Reposted with permission.

Please Support Independent Publishing We rely on advertising to deliver free magazines, newsletters, and stories at no cost to you. Please consider whitelisting our site or disabling your ad blocker to support our work. Thank you!