Fort Peck Dam outlets discharge water through tunnel 3 and tunnel 4 during open gate testing, Sept. 30, 2026, at Fort Peck Dam in Montana. The testing evaluated gate operations as part of an interagency monitoring program to protect critical water management infrastructure. (U.S. Army photo by Melani Vandall)
At A Glance
Structural Health Monitoring Initiative: Engineers from USACE Omaha District Dam Safety, the Fort Peck Project, and ERDC’s Construction Engineering Research Laboratory (CERL) conducted a field evaluation at Fort Peck Dam to establish long-term sensor monitoring for flood tunnel ring gates.
Hydraulic Capacity & Restrictions: Each of Fort Peck’s two flood tunnels features a ring gate designed to pass ~22,500 cfs fully open; current operating restrictions limit gate openings to 1 foot (~3,000 cfs).
Vibration Data & Telemetry Baseline: Collected preliminary vibration, airflow, and turbulent water flow data during gate operations to design a future long-term telemetry system and establish operational baselines.
Missouri River Water Management: Ring gates provide essential discharge capacity to manage Missouri River flows when water cannot pass through powerhouses or when reservoir drawdowns are required for safety assessments.
Key Technical Contributors: Dr. Melissa Beauregard (Omaha District Dam Safety), Dr. Brian Eick (ERDC CERL), and Jim Trogden (Fort Peck Power Plant Operations Supervisor).
Editor’s Note: The following is from USACE Omaha District, curated by America’s Engineers for general public, commercial contractor, and industry visibility. The original article can be found at the U.S. Army Corps of Engineers news repository.
Engineers from the U.S. Army Corps of Engineers, Omaha District and the Engineer Research and Development Center recently collaborated at the Fort Peck Dam to develop a long-term monitoring approach for the massive gates that help control water flow through the dam’s flood tunnels.
During a Sept. 22–23, 2026, field visit, personnel from the Fort Peck Project, Omaha District Dam Safety team and ERDC’s Construction Engineering Research Laboratory evaluated potential sensor locations and collected preliminary vibration data during limited gate operations.
U.S. Army Corps of Engineers Omaha District Fort Peck project staff assist with attaching instrumentation to ring gate control structures, Sept. 30, 2026, at Fort Peck Dam in Montana. Engineers from the Omaha District and the Engineer Research and Development Center collaborated to establish long-term structural health monitoring for the dam’s flood control gates. (U.S. Army photo by Melissa Beauregard)
Each of Fort Peck Dam’s two flood tunnels has a ring gate calculated to pass approximately 22,500 cubic feet of water per second when fully open under specified conditions. Current operating restrictions limit gate openings to 1 foot, passing approximately 3,000 cubic feet per second.
The ring gates provide an important way to manage Missouri River flows when water cannot be passed through the dam’s powerhouses. They can also help lower reservoir levels when necessary for dam safety assessments or rehabilitation.
“The ring gates are a critical component within the damming system,” said Dr. Melissa Beauregard, an Omaha District dam safety engineer. “This type of structural health monitoring data helps the district understand how the condition and performance of the gates could change over prolonged usage.”
During the field visit, the team assessed where sensors could be installed safely and practically without interfering with operations. Personnel also observed gate operations and the turbulent water flow and wind conditions that can influence sensor selection and placement.
The preliminary data will help engineers establish a baseline for comparing the gates’ responses under similar operating conditions.
“Long-term monitoring can help engineers track changes in vibration behavior under comparable operating conditions,” said Dr. Brian Eick of ERDC’s Construction Engineering Research Laboratory. “Persistent, unexplained changes could indicate a need for further engineering review or more detailed inspections.”
Water flows into the vertical shaft of Ring Gate 3 during a flow test to support a structural health monitoring study, Sept. 30, 2026, at Fort Peck Dam in Montana. The collaborative effort between the Omaha District and ERDC aims to assess the long-term performance of the massive flood tunnel gates. (U.S. Army photo by Melani Vandall)
Vibration data alone does not establish that structural damage has occurred. Engineers must consider factors such as gate position, water flow, airflow and other operating conditions when interpreting the results.
The field visit also helped the team better understand the physical layout of the gate shafts and control buildings, information that will support the design of a future telemetry system for long-term monitoring.
For Fort Peck Project personnel, establishing a baseline is especially important if future water-management needs require extended use of the gates.
“Should a long-term flow requirement through the ring gates arise, the ability to have a baseline data package would allow operators and management to monitor and understand if conditions change,” said Jim Trogden, Fort Peck Power Plant maintenance and operations supervisor. “That information can help inform decisions about further use and operation of the gates.”
The effort supports USACE’s dam safety program by combining project-level operational knowledge, district dam-safety expertise and ERDC’s structural health monitoring capabilities to better understand the performance of critical infrastructure.