Power Restored: USACE Transitions from Emergency Efforts

At A Glance: Emergency Power Restoration

  • Mission: Temporary Emergency Power Planning and Response
  • Location: Grenada, Mississippi (11 Counties Impacted)
  • Team: USACE Savannah District (SAS PRT)
  • Generators Installed: 29
  • Outcome: Power restored to water systems, schools, and critical facilities

GRENADA, MS –Following a challenging deployment in response to the January 2026 winter storm, the U.S. Army Corps of Engineers (USACE) Savannah District Temporary Emergency Power Planning and Response Team (SAS PRT) has concluded its successful mission in Mississippi. The team installed 29 generators to restore power to critical public facilities, including water systems, across 11 counties impacted by the storm.

Maj. Ben Speckhart, Vicksburg District, U.S. Army Corps of Engineers, deputy commander, looks on as members of the Savannah District Temporary Emergency Power Planning and Response Team work do deliver three emergency power generators to Lafayette Elementary School in Oxford, Mississippi. U.S. ARMY PHOTO BY LT. COL. VANESSA BOWMAN

The mission, which began on January 22, highlighted the team’s adaptability and perseverance. Initially tasked to support FEMA Region 4 in Georgia, the team was quickly re-assigned to assist Louisiana before being redirected to Mississippi.

On January 26, the team, alongside contractor WSP, established a Generator Staging Base (GSB) at Camp McCain. “Despite challenging road conditions, the first generator was installed at a critical facility just eight hours after the equipment was signed over from FEMA, which was a significant accomplishment,” said Lt. Col. Vanessa Bowman, Savannah District deputy commander and PRT mission commander.

As trees encased in ice were falling all around city of Potts Camp, Mississippi Maintenance Supervisor David Hopkins, his call for help to keep the power on for the community water pump was answered by the Mississippi Emergency Management Agency and FEMA, who dispatched the U.S. Army Corps of Engineers and their contractor, ACI, to provide temporary emergency power to the facility. The work kept the water flowing for this community in the wake of the January 2026 Winter Storm.
Music: Finding Hope Again – Eyal Goldshtein – Licensed through Megatrax.

One of the many critical infrastructures to benefit was the pumps operated by the Tri-Lake Rural Water Association. The association had about 650 residents loose water service when the storm knocked out power to their pump stations on January 25.

READ MORE: Check out other stories on USACE’s historic emergency operations in the latest edition of America’s Engineers Magazine.

“Every day since last Sunday had been a mess,” said Kevin Morris, the operator for the Tri-Lake Rural Water Association, recalling the stressful week. “There has been a lot of stress, but this was a big relief. I just about teared up seeing the Corps (of Engineers) walk up.”

To meet the widespread need, the Savannah District team established a second GSB near Tupelo, Miss. on January 31. The work at the Tri-Lake station was just one part of a much larger mission.

John Dibiase, a quality assurance specialist with the task force, spent his days checking on generators installed at various sites, including the Tri-Lake pump stations, a school, and a church.

Members of the Savannah District Temporary Emergency Power Planning and Response Team, along with Soldiers from the 249th Engineer Battalion meet in a Deployable Tactical Operation System at a Generator Staging Base at Ft. McCain in Grenada, Miss. Through its FEMA-assigned mission, USACE is working closely with the Mississippi Emergency Management Agency to identify facilities that are eligible and require temporary emergency power so, if needed, communities can get critical infrastructure such as hospitals, fire stations, warming centers, or other state-run facilities back online as quickly as possible. U.S. ARMY PHOTO

“Deploying is one of the best times to do this job,” said Dibiase, who also supported responses to Hurricanes Helene and Maria. “You are with other Corps employees who left their homes to help people. It is what we are here for.”

Over the course of the deployment, the team received 84 taskings and assessed 75 facilities. They managed 47 generator installation requests, which included navigating 14 cancellations due to utility power restoration. By the time the mission concluded, 29 generators had been successfully installed and later de-installed as local power was restored.

“This response is a true testament to the U.S. Army Corps of Engineers ability to respond to our nation when it is need,” said Adam Telle, Assistant Secretary of the Army for Civil Works. “Through every declared disaster they are called to respond to USACE continues to be the first in, and the some of the last to leave to ensure impacted communities are well on their way to full recovery.”

The mission officially concluded on February 12, after the team had systematically drawn down its presence, consolidated operations, and de-installed the final generators, leaving no remaining need for temporary power in the region.


Frequently Asked Questions: Emergency Power Mission

What is a Generator Staging Base (GSB)?

A GSB is a temporary location established during disaster response where generators and equipment are received, organized, and prepared for deployment to critical facilities in the affected area.

What is the Planning and Response Team (PRT)?

The PRT is a specialized team within USACE that is trained and ready to deploy rapidly to provide specific emergency support functions, such as temporary emergency power, debris management, or infrastructure assessment.

Who determines which facilities get generators?

FEMA and state emergency management agencies (like MEMA in Mississippi) identify and prioritize critical facilities—such as hospitals, water treatment plants, and shelters—that require temporary power, then task USACE to fulfill those needs.