Environmental Remediation & FUSRAP: USACE Buffalo District Awards $249M Contract for First Phase of Guterl Steel Site Cleanup

At A Glance

  • Major Contract Award: USACE Buffalo District awarded a contract valued up to $249 million to SA Environmental Services II for initial cleanup activities at the 70-acre former Guterl Steel Corporation site in Lockport, New York.
  • FUSRAP Authority: Addresses radiological contamination resulting from 1948–1956 rolling mill and foundry operations by Simonds Saw and Steel Co., which processed uranium and thorium under Atomic Energy Commission contracts.
  • Selected Remedy Execution: Follows the 2024 Record of Decision to address thorium-232 and uranium across site soils and industrial structures, as well as dissolved uranium in local groundwater.
  • Future Land Reuse: While current studies confirm contamination poses no immediate threat to workers, residents, or the adjacent Erie Canal, the comprehensive remediation aims to return the property to safe industrial use.
  • Program Leadership & Timeline: Directed by District Commander LTC Aaron Anderson; contractor mobilization and site field remediation are scheduled to commence in 2027 following work plan approvals.

Editor’s Note: The following is from USACE Buffalo District, curated by America’s Engineers for general public, commercial contractor, and industry visibility. The original article can be found at the U.S. Army Corps of Engineers news repository.

The U.S. Army Corps of Engineers (USACE), Buffalo District, has awarded a contract with a total value up to $249 million to SA Environmental Services II for cleanup activities at the former Guterl Steel Corporation property in Lockport, New York, under the Formerly Utilized Sites Remedial Action Program (FUSRAP).

An aerial map diagram shows site boundaries, soil contamination depths, building footprints, and groundwater extraction plans at Guterl Steel.
An engineering site plan outlines the selected remedy for the former Guterl Specialty Steel Corporation site in Lockport, New York. The technical plan details soil excavation zones, building dismantlement footprints, and groundwater treatment networks using extraction wells and rubblized trenches. USACE Buffalo District’s comprehensive remedy will prepare the 70-acre industrial parcel for beneficial reuse. (U.S. Army Corps of Engineers graphic)

Remediation is currently expected to begin in 2027 following completion and approval of required work plans and contractor mobilization.

“This contract award is a significant milestone for the Guterl Site and the Lockport community,” said LTC Aaron Anderson, USACE Buffalo District Commander. “After years of investigation, planning, and coordination, USACE is moving forward with the selected remedy to address long-term protection of human health and the environment.”

A team of USACE personnel in hard hats and safety vests walk along a gravel lane toward an aged industrial corrugated steel factory building.
Members of the USACE Buffalo District team walk past historical industrial buildings during an inspection of the former Guterl Specialty Steel site in Lockport, New York. Between 1948 and 1956, rolling mills on the property processed uranium and thorium under federal atomic energy contracts. USACE awarded a contract up to $249 million to safely dismantle contaminated structures and restore the grounds for industrial redevelopment. (U.S. Army photo by Joseph Paulin)

The contractor will develop detailed work plans that describe how the work will be performed, including health and safety procedures, environmental controls, transportation requirements, and site operations. Once USACE approves the plans, the agency will hold a public information session to present project details and answer community questions.

The Guterl Site is approximately 70 acres and is located south of Simonds Street between Ohio Street and the Lockport Bypass. The site was added to FUSRAP in 2001 because of historical operations conducted in support of the Nation’s early atomic energy program.

USACE personnel wearing hard hats, safety glasses, and reflective vests review laminated site map schematics during an outdoor inspection.
U.S. Army Corps of Engineers Buffalo District team members review structural and environmental maps during a site walkthrough at the former Guterl Specialty Steel property in September 2026. The inspection assessed facility conditions ahead of planned 2027 remediation operations under a $249 million contract. The selected remedy includes structural dismantlement and contaminated soil removal across the Manhattan Project-era site. (U.S. Army photo by Joseph Paulin)

Between 1948 and 1956, the former Simonds Saw and Steel Co. conducted foundry and rolling mill operations involving uranium and thorium metals under contract with the Atomic Energy Commission. As a result of those activities, some site buildings, soil, and groundwater were impacted by contaminants that are now addressed by FUSRAP.

An environmental technician in a hard hat and safety vest monitors testing equipment and cable reels near an open wellhead in a grassy field.
An environmental technician tests groundwater parameters at a designated monitoring well during field assessments at the former Guterl Specialty Steel site in Lockport, New York. USACE Buffalo District awarded a contract up to $249 million to execute comprehensive radiological and groundwater cleanup across the property. The work addresses historical thorium-232 and uranium contamination under the Formerly Utilized Sites Remedial Action Program. (U.S. Army photo by Joseph Paulin)

USACE released the record of decision for the Guterl Site in 2024 following years of environmental studies, public involvement, and coordination with the property owner, local officials, and regulatory agencies. The selected remedy addresses thorium-232 and uranium in soil and buildings, as well as uranium in groundwater.

A field engineer in a white hard hat and safety vest kneels to record measurements on a clipboard next to field instrumentation.
U.S. Army Corps of Engineers, Buffalo District Hydrogeologist Robert Piurek records collect temperature, pH, specific conductance, oxidation-reduction potential, turbidity, and dissolved oxygen readings from a Horiba U-52 Water Quality Monitor during annual groundwater sampling at the Formerly Utilized Sites Remedial Action Program Guterl Steel Site in Lockport, N.Y., Sept. 16, 2025. Annual groundwater sampling of the site is conducted to monitor if contamination from the nation’s early atomic energy program is moving offsite and ensure the protection of human health and the environment in the surrounding community. (U.S. Army photo by Avery Schneider)
We’re so glad you are here! Like what you’re reading? Make America’s Engineers a Google preferred news source.

Studies have shown the site contaminants do not pose an immediate threat to workers, the surrounding community, or the adjacent Erie Canal. However, USACE determined that remediation is necessary to address potential long-term risks to human health and the environment. Following completion of FUSRAP cleanup activities, the site is expected to be suitable for industrial use.

A silver USACE survey pontoon boat carrying personnel navigates along a tree-lined water corridor near rocky embankments.
USACE Buffalo District personnel conduct environmental surveillance from a work boat along the Erie Canal corridor near the Guterl Steel property. Multi-year scientific evaluations have confirmed that radiological contaminants at the site do not present an immediate threat to the adjacent canal or local waterways. Ongoing monitoring ensures water quality standards remain protected throughout upcoming FUSRAP remedial operations. (U.S. Army photo by Kaylee Wendt)

Supporting documents, including the record of decision and administrative record, are available for public review at the Lockport Public Library, 23 East Avenue, Lockport, N.Y. 14094.

A group of USACE Buffalo District military and civilian personnel in protective hard hats and high-visibility vests pose outside an industrial plant.
U.S. Army Corps of Engineers, Buffalo District personnel visit the former GUTERL Specialty Steel site in Lockport, New York, Sept. 10, 2026, ahead of planned remediation efforts at the former Manhattan Project-era site. The visit provided personnel an opportunity to assess current site conditions and prepare for upcoming work to address contamination associated with the site’s historical activities. (U.S. Army photo by Kaylee Wendt)

For additional information or to be added to the email distribution list for Guterl Site updates, email fusrap@usace.army.mil or call 800-833-6390, Option 4. Additional project information is available at: https://www.lrd.usace.army.mil/Missions/Projects/Display/Article/3612330/guterl-steel-site/

This article was originally published by the U.S. Army Corps of Engineers under the title, “U.S. Army Corps of Engineers Awards Contract for First Phase of Guterl Steel Cleanup.” Reposted with permission.