Construction crews work on the roof and upper exterior framing of the new Special Operations Forces barracks at Fort Bragg, North Carolina, Oct. 15, 2026. The 75,461-square-foot project is approximately 45 percent complete and progressing ahead of schedule. (U.S. Army photo by Ernest B. Henry IV)
At A Glance
Military Construction Milestone: The U.S. Army Corps of Engineers Wilmington District is overseeing a $43.1 million Special Operations Forces (SOF) barracks project at Fort Bragg, North Carolina, currently ~45% complete and progressing ahead of schedule.
Facility Capacity & Layout: The 4-story, 75,461-sq-ft Permanent Party Unaccompanied Housing facility will house 146 Soldiers in 4-bedroom/2-bathroom and 2-bedroom/1-bathroom modules featuring shared kitchens and living areas.
Design-Build Execution: Led by design-build contractor ACC Construction, Inc., and designer of record SLA Architects, with USACE Wilmington District managing construction quality through a three-phase inspection process.
Geotechnical Engineering Challenge: Overcame unmapped site conditions at Spartan Field by excavating six feet below grade and placing structural backfill to stabilize foundations for the four-story structure without schedule delay.
Target Milestones & Completion: Window installation starts November 2026; HVAC installation in December 2026; air barrier assembly in Feb 2027; metal roof completion in March 2027; move-in ready by spring 2029.
Editor’s Note: The following is from USACE Wilmington District, curated by America’s Engineers for general public, commercial contractor, and industry visibility. The original article can be found at the U.S. Army Corps of Engineers news repository.
The U.S. Army Corps of Engineers, Wilmington District, continues to advance military construction efforts at Fort Bragg, where a $43.1 million Special Operations Forces barracks project is approximately 45% complete and progressing generally ahead of schedule. The four-story, 75,461-square-foot Permanent Party Unaccompanied Housing facility will accommodate 146 Soldiers, providing modern living quarters designed to improve quality of life and support the installation’s housing requirements. The facility will feature a combination of four-bedroom, two-bathroom and two-bedroom, one-bathroom residential modules, each equipped with shared kitchens and living areas. The project also includes supporting infrastructure, building systems and site improvements.
A trade worker uses an angle grinder during interior mechanical and metal wall framing operations inside the Fort Bragg Special Operations Forces barracks, Oct. 15, 2026. Interior mechanical, electrical, and plumbing rough-ins are moving forward as part of the $43.1 million military construction contract. (U.S. Army photo by Ernest B. Henry IV)
ACC Construction, Inc., the project’s design-build contractor, has completed foundation work and structural steel erection. Roof installation is underway, along with interior metal wall framing and mechanical, electrical and plumbing rough-ins. Exterior work includes installation of the air barrier assembly, masonry façade and storm drainage systems. The project team has also completed and turned over a new basketball court and picnic area adjacent to Patriot Point Physical Fitness Center.
According to Wes Clark, project engineer for the Wilmington District’s USASOC-A Resident Office, the project’s favorable progress reflects detailed planning and coordination among the construction contractor, design professionals, USACE and installation stakeholders. During the design phase, timely input from multiple stakeholders, including installation housing, engineering and environmental directorates, helped maintain project momentum. Continued collaboration between ACC Construction and SLA Architects, the designer of record, has also supported timely material procurement and design clarifications.
The team encountered a significant challenge early in construction when site conditions at Spartan Field, a portion of the 108th Air Defense Artillery Brigade’s parade field, required additional preparation to support the four-story structure. Working together, USACE and the design-builder developed a solution involving excavation approximately six feet below grade and installation of structural backfill to establish suitable foundation conditions. The work was accomplished without delaying the scheduled start of construction.
Construction crews advance exterior masonry and air barrier installation on a four-story Special Operations Forces barracks at Fort Bragg, North Carolina, Oct. 15, 2026. The $43.1 million USACE Wilmington District facility will accommodate 146 Soldiers upon completion in 2029. (U.S. Army photo by Ernest B. Henry IV)
As the construction agent, Wilmington District oversees contract execution, design compliance, construction quality and schedule management. The district employs a three-phase quality control process consisting of preparatory, initial and follow-up inspections to verify that materials and construction activities meet contract requirements. This approach helps minimize rework, maintain quality standards and support timely project delivery. The district also coordinates with utility and telecommunications partners and supports planning for furniture, fixtures and equipment procurement in collaboration with installation housing officials and the U.S. Army Engineering and Support Center, Huntsville.
Upcoming construction milestones include window installation beginning in November, installation of residential heating, ventilation and air conditioning equipment beginning in December, completion of the air barrier assembly in February 2027 and completion of the metal roof in March 2027. The project’s favorable construction progress is expected to support earlier procurement and installation of furniture, fixtures and equipment, with the facility currently projected to be move-in ready by spring 2029.
Once complete, the barracks will provide modern housing for 146 Soldiers, reflecting the Wilmington District’s continued commitment to delivering quality infrastructure that supports Army readiness and improves Soldiers’ quality of life.